8.6 C
Liverpool
Thursday, April 18, 2024

Latest Posts

Liverpool City Council appoint Contractors to complete stalled highways schemes

Liverpool City Council appoint contractors to complete the remaining highways schemes which had stalled following the collapse of VIAM.

Five schemes in total, which had a combined £4.9m of work left to complete, were affected when the company went into administration in the summer.   

Contractors for two of these schemes, which were less complex in nature – resurfacing on Kingsley Road in Toxteth and new lighting on County Road (A59) in Walton – were appointed via the council’s planned works framework. 

The lighting works, carried out by Siemens, have completed and Huyton Civils will finalise works on Kingsley Road in the next two weeks.   

Following a rigorous tendering process, contractors have now been appointed for the remaining schemes:   

* A59 / County Road and Walton Lane – resurfacing, ducting, kerbing and other civils, delivered by Huyton Asphalt Ltd.   
* A565 / Derby Road – resurfacing, ducting, kerbing and other civils, delivered by Dowhigh Ltd.   
* Byrom Street – pedestrian crossing, delivered by Colas.   

Each scheme will be subject to site investigations to validate works completed to date and to establish what works are left to be undertaken.   

Various works across the sites will be carried out over the coming weeks, weather permitting, and will then pause for the city’s Christmas break which will begin 26 November, resuming 9 January 2022. The Byrom Street scheme will however continue and is scheduled to complete in mid- December.

Councillor Daniel Barrington, Cabinet member for Climate Emergency, Transport and Environment, said:

“The stalling of these highways schemes was a huge blow. We share the frustrations of everyone affected and we apologise for the delays. “The varying nature of these schemes has presented numerous challenges to get the works back on track and although we’ve moved as fast as possible, we know it’s not been as fast as people wanted. 

“The upgrades to the A59 and A565, in particular, are more complex and costly as they are of huge consequence to our overall highways network and their completion requires many more steps in the tendering process. “I’m delighted that we’ve now appointed contactors to resume these schemes. The Christmas break will unfortunately mean they won’t complete this year, but they will be done in the first few months of 2022.  “The stalling of Lime Street has further tested people’s patience which I understand.  

“Our Highways team are working flat out to get this hugely important scheme back on its feet as quickly as possible, and I’m confident that by the run up to Christmas the site will be more accessible for pedestrians than it currently is.”

Liverpool City Council is also currently making a full site assessment of Lime Street, following the collapse of the scheme’s contractor – NMCN – and will advertise the completion tender in December.     

READ MORE: Merseyrail celebrates 50 years of service

Latest Posts

Don't Miss

Stay in touch

To be updated with all the latest news, offers and special announcements.